60 MWp O&M Takeover & Recovery — Madhya Pradesh
Madhya Pradesh, India · Utilities & IPPs
Overview
Takeover of a 60 MWp plant running at 71% performance ratio, recovered to 82% within two quarters under a PR-guaranteed O&M contract.
The challenge
The plant was generating 13% below its simulation and nobody could say why. Monitoring was at inverter level only, so string outages had gone unnoticed for months, and the cleaning cycle was a fixed monthly visit regardless of soiling.
What we did
We installed string-level monitoring with alarm escalation, ran full IV curve tracing and thermographic scans to find 214 underperforming strings and 38 hot joints, and reset cleaning to a soiling-rate driven cycle. PR moved from 71% to 82.3% in two quarters, with monthly actual-versus-simulated reporting to the lender.
Project data
| Capacity | 60 MWp DC |
|---|---|
| PR on Takeover | 71.0% |
| PR After Recovery | 82.3% |
| Strings Rectified | 214 underperforming, 38 hot joints |
| Monitoring | String level, 24x7 with escalation |
| Recovery Period | 2 quarters |
Standards applied
- IEC 61724
- IEC 62446-1
- IEC 62446-3
- ISO 45001
Scope supplied
- Comprehensive O&M
- Thermography & IV Testing
- Plant Revamping
- Remote Monitoring